An Electrical Installation Certificate (EIC) is the BS 7671 form for new electrical work: a new installation, one or more new circuits, or a replacement consumer unit or distribution board. Work that adds no new circuit can go on a minor works certificate, and an existing installation gets an EICR. ClearWorks issues all three on site.
Last updated
- From £15 a month + VAT, unlimited certificates
- 3 free certificates, no card needed
When do you need an EIC instead of minor works or an EICR?
The notes on the IET’s BS 7671:2018+A4:2026 model EIC, dated 15 April 2026, say it is used for:
- the initial certification of a new installation
- an addition or alteration where one or more new circuits have been introduced
- replacing a consumer unit or distribution board
- several additions, alterations or remedial jobs on one installation, as an alternative to several minor works certificates
The same notes say it is not to be used for periodic inspection and testing.
| Form | Use it for | Example |
|---|---|---|
| Electrical Installation Certificate (EIC) | New installation, new circuit, or replacement consumer unit or distribution board | A new cooker circuit, a full rewire, a consumer unit change |
| Minor works certificate | An addition or alteration to an existing circuit that adds no new circuit | An extra socket-outlet on an existing ring, moving a light switch |
| EICR | Reporting on the condition of an installation already in service | A landlord’s 5-yearly inspection |
For the full explainer, including who signs and what a homeowner should keep, read our guide to the Electrical Installation Certificate.
Is EIC work notifiable under Part P?
Often, but the two are separate. The EIC is a BS 7671 certificate. Notifying the work is a Building Regulations duty. In England, regulation 12(6A) of the Building Regulations 2010 makes Part P work notifiable when it involves:
- the installation of a new circuit
- the replacement of a consumer unit
- any addition or alteration to existing circuits in a special location
So a new circuit needs an EIC and is notifiable. An alteration to an existing circuit in a special location, such as near a bath, adds no new circuit and can go on a minor works certificate, but it is still notifiable.
If you are registered with a competent person scheme, you notify through the scheme. Under regulation 20, the occupier must get a copy of the Building Regulations compliance certificate within 30 days of completion. These rules are for England. See our Part P guide for the other routes.
What does the EIC record?
The Amendment 4 model form records:
- Client and installation. Who the work is for, the address, and whether it is a new installation, an addition or an alteration, with its extent.
- Three declarations. Design, construction, and inspection and testing, each signed by the person responsible, with any departures from BS 7671.
- Next inspection. The recommended interval before the installation is inspected and tested again.
- Supply and earthing. Supply characteristics, earthing arrangements and particulars of the installation.
- Comments on the existing installation. For an addition or alteration.
- Schedules. A schedule of inspections, a schedule of circuit details and a schedule of test results.
The form says the certificate is only valid if the schedule of inspections has been completed and the schedules of circuit details and test results are attached.
How ClearWorks handles the EIC
ClearWorks is a gas and electrical certificate app for UK engineers. The EIC sits beside the EICR and the minor works certificate, all to BS 7671:2018+A4:2026.
- Missing details and readings outside limits are flagged
- Zs checked against the protective device
- No signing with something missing, no sending without your registration number and signatures
- Works with no signal, on phone, tablet and desktop
When you sign, the certificate goes to your customer with your logo, and you get a record of when it was opened. It stays in the property’s certificate history. Invoice from the same place and take card payment to your own account.
ClearWorks checks each certificate against the form’s rules. Choosing the right form, notifying the work, and the work, the testing and the certificate remain your responsibility. ClearWorks is not affiliated with or endorsed by NICEIC, NAPIT or ELECSA.
EIC questions
Do I need an EIC for a consumer unit change?
Yes. The notes on the BS 7671:2018+A4:2026 model EIC list replacing a consumer unit or distribution board as work the certificate is used for. A minor works certificate is not for that job.
Can one EIC cover several small jobs?
Yes. The model form notes say an EIC can be used for multiple additions, alterations or remedial works on one installation, as an alternative to issuing several minor works certificates.
Does issuing an EIC notify building control?
No. The EIC is a BS 7671 certificate. In England, notifiable Part P work is notified separately, through your competent person scheme, a third-party certifier or building control.
Will a landlord in England accept an EIC as confirmation of remedial work?
Government guidance for England lists an Electrical Installation Certificate as one acceptable form of written confirmation that remedial work has been carried out.
Can I use an EIC for a periodic inspection?
No. The model EIC says it is not to be used for periodic inspection and testing. That is what the EICR is for.
Sources: IET, BS 7671:2018+A4:2026 model Electrical Installation Certificate (dated 15 April 2026). IET, BS 7671 model forms. Building Regulations 2010, regulation 12. Building Regulations 2010, regulation 20. GOV.UK, Electrical safety standards in the private and social rented sectors: guidance. Last checked 25 November 2026.
Related
Issue your next EIC in ClearWorks.
Your first 3 certificates are free. No card needed.
Founding London engineers keep their price for as long as they stay subscribed.