An EIC certifies new electrical work: a new installation, a new circuit or a replacement consumer unit. This guide covers what the Amendment 4 form contains, who signs it, and how it differs from a minor works certificate and an EICR.

Last updated

What an EIC is

An Electrical Installation Certificate (EIC) is the BS 7671 form that certifies new electrical work. The IET publishes it as a free model form. Its guidance for recipients says it confirms that the work has been designed, constructed, inspected and tested in accordance with BS 7671.

The notes on the IET’s Amendment 4 model EIC (dated 15 April 2026) say the form is used for:

  • the first certification of a new installation
  • an addition or alteration to an existing installation where one or more new circuits have been added
  • replacing a consumer unit or distribution board
  • several additions, alterations or remedial jobs on one installation that add no new circuit, as an alternative to issuing several minor works certificates

This page is a summary for electricians and for people who receive an EIC. It is not the standard. Work from the published BS 7671:2018+A4:2026, the IET model forms and your scheme’s guidance. You remain responsible for the work, the testing and the certificate. ClearWorks is not affiliated with or endorsed by the IET, BSI, NICEIC or NAPIT.

EIC, minor works certificate or EICR?

The three main BS 7671 model forms, and when to use each
FormUse it for
Electrical Installation Certificate (EIC)A new installation, a new circuit, or a replacement consumer unit or distribution board.
Minor Electrical Installation Works CertificateAn addition or alteration that does not add a new circuit, such as an extra socket-outlet on an existing circuit.
Electrical Installation Condition Report (EICR)Periodic inspection and testing of an installation that is already there.

An EIC certifies new work. An EICR reports on the condition of an existing installation. For the report layout, see the EICR template.

Who signs an EIC

The Amendment 4 model form has three separate declarations. Each is signed by the person responsible for that part of the job.

  • Design. There is room for two designers where responsibility for the design is shared.
  • Construction. The person responsible for installing the work.
  • Inspection and testing. The person who inspected and tested it.

Each declaration has a space for any departures from BS 7671.

If you did all three, the form’s notes say a signatory authorised for more than one category signs in each of the places. The notes also refer to a single-signature EIC, where one person authorised for all three signs once. The IET’s Amendment 4 download contains the three-declaration form only, so check which version your scheme or software provides.

What is on the Amendment 4 EIC

The model form runs from Section A to Section J, followed by two schedules.

  • Client and installation. Who the work is for, the address, and whether it is a new installation, an addition or an alteration, with its extent.
  • Signatories. The three declarations above, and the details of the people and companies who signed.
  • Next inspection. The designer recommends the longest interval before the installation is inspected and tested again.
  • Supply and earthing. Supply characteristics, earthing arrangements, and particulars of the installation.
  • Schedule of inspections. Fourteen headings, from the intake equipment to prosumer’s installations, each marked with an outcome or as not applicable.
  • Comments on the existing installation. For an addition or alteration.
  • Schedule of circuit details. For each circuit: conductors, the overcurrent device, the RCD and the maximum permitted Zs.
  • Schedule of test results. For each circuit: continuity, insulation resistance, polarity, measured Zs, and RCD and AFDD tests, with the test instruments used.

The form says the certificate is only valid when the schedule of inspections is complete and the schedules of circuit details and test results are attached.

Where to get the form

The blank Amendment 4 EIC is free on the IET model forms page. The IET lets you copy and adapt the forms free of charge for use in your own electrical contracting business. You must not resell blank copies or put the IET logo on yours, and the IET does not check your version for errors. The page lists one EIC for Amendment 4, with no separate domestic version.

Building Regulations notification in England

The EIC is a BS 7671 document. Notifying the work under the Building Regulations is a separate duty, with its own certificate. In England, regulation 12(6A) of the Building Regulations 2010 makes electrical work covered by Part P notifiable when it is:

  • the installation of a new circuit
  • the replacement of a consumer unit
  • an addition or alteration to an existing circuit in a special location: the defined space around a bath or shower, or a room containing a swimming pool or sauna heater

Approved Document P says other electrical work is not notifiable, but should still be inspected, tested and certificated to BS 7671. It gives three routes for notifiable work.

  1. Self-certification. An installer registered with a competent person scheme completes a BS 7671 EIC and gives it to the person who ordered the work. Within 30 days of completion, the installer or the scheme gives the occupier a Building Regulations compliance certificate and tells building control.
  2. Third-party certification. An installer who is not registered appoints a registered third-party certifier before work begins, and notifies them within 5 days of finishing.
  3. Building control. Otherwise the installer notifies a building control body before work begins. It decides what inspection and testing it needs, then issues a completion certificate or final certificate.

The two tests do not match exactly. A new circuit needs an EIC and is notifiable. Altering an existing circuit in the defined space around a bath adds no new circuit, so a minor works certificate can cover it, but the work is still notifiable. GOV.UK lists the authorised competent person schemes for electrical work in dwellings.

This section covers England. The Wales version of regulation 12 does not contain paragraph (6A).

What a homeowner or landlord should keep

The form’s notes say the original EIC goes to the person who ordered the work, and the electrician keeps a duplicate. Its guidance for recipients adds:

  • If you ordered the work but don’t own the installation, pass the certificate and its schedules to the owner straight away.
  • Keep the original somewhere safe, and show it to anyone who inspects or works on the installation later.
  • If you move out, it shows the new owner that the work met BS 7671 when the certificate was issued.

For notifiable work, keep the Building Regulations compliance certificate, or the building control completion certificate, with it.

When you sell

The Law Society’s notes to the TA6 property information form (6th edition) tell sellers that most electrical work requires one of three documents: a building control completion certificate, the installer’s Building Regulations compliance certificate, or the BS 7671 Electrical Installation Certificate. If you have one, you attach it to the form. The same notes say an EICR is not a legal requirement for a sale in England and Wales.

Where ClearWorks fits

ClearWorks covers the EIC, the EICR and the minor works certificate, all to BS 7671:2018+A4:2026.

  • EIC. For new circuits, rewires and consumer unit changes.
  • EICR. Observations coded C1 to FI, and Zs checked against the protective device.
  • Minor works. Linked to the EICR findings it fixes.

The electrical plan is £15 per engineer a month + VAT. New forms are added to your plan at no extra cost.

See the EICR software

Sources: IET, BS 7671 model forms (forms listed, conditions of use, minor works form). IET, BS 7671:2018+A4:2026 model Electrical Installation Certificate (when the form is used, signatories, sections, schedules, guidance for recipients). Building Regulations 2010, regulation 12 (notifiable work and special locations, England). Building Regulations 2010, regulation 20 (30 days). GOV.UK, Approved Document P, 2013 edition (the three certification routes). GOV.UK, competent person schemes. The Law Society, TA6 (6th edition) explanatory notes.

Last checked 18 November 2026. ClearWorks is not affiliated with or endorsed by the IET, BSI, NICEIC, NAPIT or the Law Society. This guide is not legal advice.

Questions about the EIC

What is an Electrical Installation Certificate?

It is the BS 7671 form that certifies new electrical work. It confirms the work was designed, constructed, inspected and tested in accordance with BS 7671. It is not used to report on an existing installation.

When do I need an EIC instead of a minor works certificate?

The IET model form says an EIC is used for a new installation, an addition or alteration that adds one or more new circuits, or a replacement consumer unit or distribution board. An addition or alteration that adds no new circuit can go on a minor works certificate.

Is there a separate domestic electrical installation certificate?

The IET model forms page lists one Electrical Installation Certificate for BS 7671:2018+A4:2026, with no separate domestic version. If your scheme or software offers a domestic or single-signature version, check it against the current model form.

Is an EIC the same as a Building Regulations compliance certificate?

No. The EIC is the BS 7671 certificate the electrician gives to the person who ordered the work. In England, for notifiable work done by a registered competent person, the occupier also receives a Building Regulations compliance certificate within 30 days of completion.

Is a minor works certificate enough for an extra socket?

Yes, if the socket-outlet is added to an existing circuit. A new circuit needs an EIC.

Related pages

EIC, EICR and minor works on your phone

Your first 3 certificates are free. No card needed.

Founding London engineers keep their price for as long as they stay subscribed.

Get 3 free certificates